This guide explains how to wire and mount the GEM120CT correctly to ensure accurate readings.
Step-by-Step Installation
- Isolate power before working on the system.
- Mount the GEM120CT on a DIN rail in the distribution board.
- Connect voltage references:
Meter Terminal – 3 – Neutral (N) – Neutral supply
Meter Terminal – 4 – Live (L1) – Live grid feed - Install CT clamp:
- Place around the live cable only (not neutral).
- Arrow on clamp must face toward the property load.
- Connect CT clamp wires to the bottom of the meter:
Port – 1 – White – CT+
Port – 2 – Black – CT-
- Tighten all terminals and ensure the CT clamp is fully closed.
- Power on the system and confirm LED activity.
Notes
- Do not extend or shorten CT wires as this will cause inaccurate readings.
- Use a single live conductor within the clamp only.